Summary
Open Doors Management is pleased to present a 60 acre energy storage development site for lease in Benton County, TN. The property sits next to a 161 KV substation in the Tennessee Valley Authority Electrical Grid Network. Ownership has agreed to a 40-year  ground lease. The property sits within an Energy Community as it is located near the recently retired Johnsonville Power Plant. TVA would support future developement of an energy storage site as they have recently committed to developing 5.000 MW of renewable energy throughout their network.
Please contact Lane.Sharman@opendoors.com to obtain an exclusive right to negotiate a Lease.
Latitude35.879577
Longitude-88.159739
Infrastructure Mapping Information, Open Doorshttps://www.arcgis.com/home/webmap/viewer.html?webmap=f928f314504444d8a2d459fc40d2cc07&find=-88.159739,35.879577
Site Image
KMZ FileTN Benton Hicks Parcel (only).kmz
Term Sheethttps://docs.google.com/document/d/e/2PACX-1vSCpdtp7XwfjbJjHcnOIeZL0dupvPpHiO9uPwuqwYS7kn3q2mCqYYr07WalHup8MgQbNzZh_WBeV_wt/pub
CountyBenton
StateTN
Legal OwnerHicks James Matthew Etux Courtney & Hicks James Matthew Etux Courtney Lean
DO NOT CONTACT
For Information
Lane Sharman +1-858-342-1415 lane.sharman@opendoors.com
Energy Community?
AssignmentLane Sharman
Listing URLhttps://www.ragic.com/ozquantum/real-estate/6/16?embed&hidetop&embedEntry&rmlc=u40oFA7cG88fr20240315212734ozquantum%2Freal-estate%2F6
Local UtilityTennessee Valley Authority (TVA)
Interconnection Brief
- Single line 161KV substation owned and operated by Tennessee Valley Authority
-161KV substation is a drop point for transmission running from Johnsonville Power  Plant and western Tennessee
-Substation interconnects via a three line tap north of the property
Owner & Site Brief12-5-2023 Owner terminated management agreement with Open Doors.
Single Party Owner with 40 Year pre-negotiated Lease as Follows:
-3 Year Development Phase
-30 Year Base Term with Two 5 Year Extentions
-2% Annual Rent Increase
-Tenant to pay NNN
Development Brief-Land is currently zoned for agricultural use
-Southern portion of the property is wooded and in flood zone
-Owner has easement to substation
Site Analyticsfloodrisk.PNG
Listing Sequence Number16
Site Characteristics
TypeNotesMap URLImageFileCharacteristic SeqNbr
Queue AnalysisConsult this queue prior to any final land acquisition decision.https://www.arcgis.com/home/webmap/viewer.html?webmap=f928f314504444d8A2d459fc40d2cc07&find=,  00621